Town Bridges Pending or Under Repair

NH DoT Project 40649

Upper Bell Hill Bridge on Hill Road

NH DoT Status: Closed, under construction​

Next Steps: The Turner Group to complete construction and open Hill Road by June 26, 2026

NH DoT contract 8-1-2023

Hoyle Tanner Engineering Design contract 4-21-2024

NH DES Wetlands Permit 6-11-2025

NH DoT BA of TTG & E.D. Swett 8-1-2025

The Turner Group (TTG) Construction Reports

Updates to Permits

NH DoT Project 40661

Comstock Road Bridge

 

NH DoT Status: Red-Listed, open to traffic

Next Steps: After Hill Road opens, close Comstock Road and begin construction

NH DoT contract 8-1-2023

Hoyle Tanner Engineering Design contract 4-21-2024

NH DoT Approval of Hoyle Tanner Design 2-13-2026

NH DES Wetlands Permit 3-11-2026

Hoyle Tanner Construction Bid Specs 3-26-2026

NH DoT BA of Neil H Daniels LLC 4-23-2026 

NH DoT Project # pending, ToA-1 for now

Thayer Brook Road Bridge

NH DoT Status: Closed, bypass in place

Next Steps: Waiting for FEMA reimbursement

NH DoT contract - Pending

Engineering contract - Pending

NH DES Wetlands Permit - Pending

Other Information

NH DoT Project 44388

Drewsville Road Bridge

NH DoT Status: Red-Listed, open to traffic

Next Steps:

Signed Letter 8-1-2025

NH DoT contract 8-1-2025

Engineering Design contract - Pending

NH DES Wetlands Permit - Pending

Other Information

NH DoT Project # pending, ToA-2 for now

Lower Bell Hill Bridge on Hill Road

NH DoT Status: Red-Listed

Next Steps: Waiting for Projects 1, 2, and maybe 4 to be completed.

NH DoT Contract - Pending

​NBRC Timber for Transit Grant - Submitted

Engineering Contract - Pending Grant 

NH DES Wetlands Permit - Pending

Other Information