top of page

Major Town Bridge Projects

NH DoT Bridge Project #40649

Upper Bell Hill Bridge on Hill Road

over Darby Brook - Bridge #059/134

​

NH DoT Status: Open to 2-way traffic, but not yet Completed.​

Next Steps: Finish the remaining tasks and remove the construction trailer from Cook Hill road.​

QBS Approval 3-14-2023

NH DoT contract 8-1-2023

Hoyle Tanner Engineering Design contract 4-21-2024

​NH DES Wetlands Permit 2025-00373 6-11-2025

NH DoT BA of TTG & E.D. Swett 8-1-2025

Updates to Permit 2025-00373​ 8-7-2025

Change Order #1 Approval 6-5-2026

Cost Estimate Amendment #1 Approval 7-16-2026

Change Order #2 Approval 9-8-2026

Bridge Construction Progress Reports

NH DoT Bridge Project #40661

Comstock Road Bridge over

Darby Brook - Bridge #046/141

 

NH DoT Status: Open to 1-way traffic.

Next Steps: Closure for construction is currently scheduled for February of 2027.

QBS Approval 3-14-2023

NH DoT contract 8-1-2023

Hoyle Tanner Engineering Design contract 4-21-2024

NH DoT Approval of Hoyle Tanner Design 2-13-2026

NH DES Wetlands Permit 2025-02745 3-11-2026

Hoyle Tanner Construction Bid Specs 3-26-2026

NH DoT BA of Neil H Daniels LLC 4-23-2026

Notice to Proceed 7-27-2026 ​

Amended NH DoT contract 9-8-2026

NH DoT Bridge Project #44388

Drewsville Road Bridge over

Darby Brook - Bridge #058/132

​​

NH DoT Status: Red-Listed, Open to 2-way traffic.

Next Steps: Waiting for completion of Projects 40649 and 40661.

Signed Letter 8-1-2025

NH DoT contract​ 8-1-2025

Engineering Design contract - Pending

NH DES Wetlands Permit - Pending

Other Information:

Alstead Bridge Project #2026-1

Thayer Brook Road Bridge

over Thayer Brook - Bridge #148/175

​​

Current Status: Closed, 2-way Bypass in place.​

Next Steps: Waiting for FEMA reimbursement.

Engineering Design contract - Pending

NH DES Wetlands Permit - Pending

Other Information: This is the only major bridge project not dependant on the completion of the other 4 major bridge projects. It is also not being repaired under NH DoT guidelines.

Alstead Bridge Project - 2026-2

Lower Bell Hill Bridge on Hill Road

over Darby Brook - Bridge #058/136

​

NH DoT Status: Red-Listed, Open to 2-way traffic.

Next Steps: Waiting for NH DoT Projects #40649, #40661 and #44348 to be completed.

NH DoT Contract - Pending

​NBRC Timber for Transit Grant - Approved 6-21-2024

SWRPC / NBRC Eng Grant - Approved 5-22-2026

SWRPC / NBRC Pre Application - Submitted 8-20-26

SWRPC / NBRC Const Grant - Pending

GM2 Engineering Design Contract

NH DES Wetlands Permit - Pending

Other Information​: From the Town's perspective, the Engineering Design can begin at any time, but this bridge cannot be closed for construction until the other three Darby Brook bridge projects are completed.

bottom of page