Town Bridges Pending or Under Repair
NH DoT Project 40649
Upper Bell Hill Bridge on Hill Road
NH DoT Status: Closed, under construction
Next Steps: The Turner Group to complete construction and open Hill Road by June 26, 2026
NH DoT contract 8-1-2023
Hoyle Tanner Engineering Design contract 4-21-2024
NH DES Wetlands Permit 6-11-2025
NH DoT BA of TTG & E.D. Swett 8-1-2025
NH DoT Project 40661
Comstock Road Bridge
NH DoT Status: Red-Listed, open to traffic
Next Steps: After Hill Road opens, close Comstock Road and begin construction
NH DoT contract 8-1-2023
Hoyle Tanner Engineering Design contract 4-21-2024
NH DoT Approval of Hoyle Tanner Design 2-13-2026
NH DES Wetlands Permit 3-11-2026
Hoyle Tanner Construction Bid Specs 3-26-2026
NH DoT BA of Neil H Daniels LLC 4-23-2026
NH DoT Project # pending, ToA-1 for now
Thayer Brook Road Bridge
NH DoT Status: Closed, bypass in place
Next Steps: Waiting for FEMA reimbursement
NH DoT contract - Pending
Engineering contract - Pending
NH DES Wetlands Permit - Pending
Other Information
NH DoT Project 44388
Drewsville Road Bridge
NH DoT Status: Red-Listed, open to traffic
Next Steps:
Signed Letter 8-1-2025
NH DoT contract 8-1-2025
Engineering Design contract - Pending
NH DES Wetlands Permit - Pending
Other Information
NH DoT Project # pending, ToA-2 for now
Lower Bell Hill Bridge on Hill Road
NH DoT Status: Red-Listed
Next Steps: Waiting for Projects 1, 2, and maybe 4 to be completed.
NH DoT Contract - Pending
NBRC Timber for Transit Grant - Submitted
Engineering Contract - Pending Grant
NH DES Wetlands Permit - Pending
Other Information