Major Town Bridge Projects

NH DoT Project 40649

Upper Bell Hill Bridge on Hill Road

over Darby Brook

NH DoT Status: Closed, under construction.​

Next Steps: The Turner Group / E. D. Swett to complete substantial construction and open Hill Road to all traffic by August 21, 2026 (change order #1).

NH DoT contract 8-1-2023

Hoyle Tanner Engineering Design contract 4-21-2024

NH DES Wetlands Permit 2025-00373 6-11-2025

NH DoT BA of TTG & E.D. Swett 8-1-2025

Bridge Construction Progress Reports

Updates to Permits

Change Order #1 6-5-2026

NH DoT Project 40661

Comstock Road Bridge

over Darby Brook

 

NH DoT Status: Red-Listed, open to traffic.

Next Steps: After Bridge Project 40649 opens to traffic, close this bridge to traffic and begin construction.

NH DoT contract 8-1-2023

Hoyle Tanner Engineering Design contract 4-21-2024

NH DoT Approval of Hoyle Tanner Design 2-13-2026

NH DES Wetlands Permit 2025-02745 3-11-2026

Hoyle Tanner Construction Bid Specs 3-26-2026

NH DoT BA of Neil H Daniels LLC 4-23-2026 

NH DoT Project 44388

Drewsville Road Bridge

over Darby Brook

NH DoT Status: Red-Listed, open to traffic.

Next Steps: Waiting for completion of Projects 40649 and 40661.

Signed Letter 8-1-2025

NH DoT contract 8-1-2025

Engineering Design contract - Pending

NH DES Wetlands Permit - Pending

Other Information:

Town of Alstead Project 202x-01

Thayer Brook Road Bridge

over Thayer Brook

Current Status: Closed, bypass in place.

Next Steps: Waiting for FEMA reimbursement.

Engineering Design contract - Pending

NH DES Wetlands Permit - Pending

Other Information: This is the only major bridge project not dependant on the completion of the other 4 bridge projects, and not being repaired under NH DoT guidelines. No NH DoT money, hence no NH DoT contract.

NH DoT Project - pending, 202x-02 for now

Lower Bell Hill Bridge on Hill Road

over Darby Brook

NH DoT Status: Red-Listed, open to traffic.

Next Steps: Waiting for NH DoT Projects 40649, 40661 and 44348 to be completed.

NH DoT Contract - Pending

NBRC Timber for Transit Grant - Approved 6-21-2024

SWRPC Sub Grant - Approved 5-22-2026

GM2 Engineering Design Contract

NH DES Wetlands Permit - Pending

Other Information​: From the Town's perspective, the Engineering Design can begin at any time, but this bridge cannot be closed for construction until the other three Darby Brook bridges are completed.